Railway Station Zürich, Zürich, Swizerland

The story

Underground station of Zürich. Construction work was carried out in top down method. The basement flor slab and the walls have been sealed with BPA-CEMtobent® bentonite lining systems. As joint sealing we used CEMproof PVC waterstop tapes and bentonite waterstop BPA-Quellmax® Plus.

More projects

  • Hosptial Höchst / DE
  • Funkkaserne Munich / DE
  • Haribo Office and Administration building  / DE
references

Installed systems

  • Bentonite waterstop BPA-Quellmax® Plus
  • Bentonite lining system BPA-CEMtobent®
  • BPA-PVC Waterstop
product overview

For further information please feel free to contact us

+49 (0) 7032 / 89 399-0